Previous Page  74 / 298 Next Page
Information
Show Menu
Previous Page 74 / 298 Next Page
Page Background

Risk Management in Transport PPP Projects

In the Islamic Countries

55

The main possible drivers for early termination are three (The World Bank et al., 2017):

Default by the private party

;

Termination by the public party

(for reasons of public interest or due to default);

Early termination because of an external reason (force majeure)

.

Under each option, the public authority makes a payment to the private party and takes over the

ownership of the project assets, which may be subsequently re-tendered through a new PPP

process. Crucially, the PPP contract should specify the process of claiming, determining, and

implementing the compensation (APMG, 2016).

Such provisions ensure that, should the basis of the PPP contract be challenged by events, an

orderly process can be conducted and thus uncertainty can be reduced (EPEC, 2013).

The rationale behind compensation payments lies in the consideration that, whenever a

termination event occurs, the party negatively affected is entitled to be compensated in order to

offset the loss (material or potential) suffered, such as for instance forgone revenues. Further,

compensation to the private party is granted in order not to undermine the business

environment and not to disincentivize lenders to PPP projects. However, it is key for the

compensation not to be too high, as this might generate additional risks related to moral hazard.

Three main approaches to compensation can be outlined (APMG, 2016; EPEC, 2013):

Market value

: typical approach in common law countries, where the compensation is

determined by reference to the market value of the PPP contract at the date of termination.

Alternatively, the public authority may decide to replace the private party by tendering out

the position of equity. This approach is considered fair as it is strictly connected to what

the impaired contract is effectively worth. It also avoids contract cancellation and does not

devote public resources to the compensation;

Debt based compensation

: the compensation equals the value of the outstanding senior

debt. This approach, however, as it is more favorable to the government, may create

incentives to terminate early the contract. Moreover, this mechanism may undermine

lenders’ incentives to conduct thorough due diligence and careful project monitoring;

Book value

: typical approach of civil law countries, where the compensation is based on

the book value of the asset, i.e. considering the sums invested by the private party to build

the project and focusing on the value of the project assets rather than the value of the

contract, in contrast to the market value approach.

Follow up

Marcelo et al. (2017) highlight that experience in dealing with PPPs reduces the probability of

contract cancellation. In addition, the benefits of learning are found by the same study to be

mostly concentrated in the first PPP arrangements: after a country closes a relatively low

amount of PPP contracts, the likelihood of contract cancellation rapidly declines. This finding

particularly holds for transport PPPs.