Previous Page  71 / 298 Next Page
Information
Show Menu
Previous Page 71 / 298 Next Page
Page Background

Risk Management in Transport PPP Projects

In the Islamic Countries

52

allowing for quicker and more efficient check-in, baggage drops or security checks (Global

Infrastructure Hub, 2016).

The

force majeure risk

consists in external events beyond the control of the parties (such as

natural disasters, war or civil disturbance) affecting the project. It is typically shared between

the private and the public party. As a mitigation measure, project insurance can be put forward

in order to mitigate force majeure risks causing physical damage and loss of revenue coverage.

These five illustrative risks, as well as the other threats potentially materializing during the

operation phase, need to be subject to a strict

monitoring

process covering the whole duration

of the operation phase, which represents a prerequisite for their effective

mitigation

or

treatment

.

Bonus/malus schemes

As foreseen during the contracting stage, in a transport PPP remuneration of the private party

is linked to the project’s performance. At the operation stage, in case the outputs or targets

provided for in the contractual arrangement have not been achieved, this link can translate into

penalties

(or fines) for the private party. Concretely, penalties can be put in place through

deductions on payment, or fines to be paid by the private party. Vice versa, if the targets have

been achieved,

bonus payments

might be delivered by the public authority to the private party.

These schemes can be applied for both government-pay and user-pays PPPs (The World Bank

et al., 2017).

Contract renegotiation

Due to the impossibility to anticipate all the events that may occur during the contract period

and future scenario, PPP contracts are intrinsically incomplete. Therefore, they may need

adjustment in response of unforeseen events.

Unforeseen events might require a realignment in the project objectives and a new balance of

the

risk sharing

between public and private parties.

The word “

renegotiation

” relates to changes in contractual provisions, often implemented as a

mechanism to avoid project cancellation when unforeseeable events occur. Such changes

represent one solution to ensure

risk treatment

during the project implementation phase.

The causes of renegotiations are heterogenous. While in certain circumstances a degree of

flexibility becomes necessary and renegotiation is identified as the way to achieve it, in other

cases renegotiations are driven mainly by opportunistic behaviors which undermine fair

competition.

For instance, financial and macroeconomic shocks may undermine the initial project idea (as

PPPs entail large sunk investments and a great exposure to financial market to finance them)

and ultimately require contractual changes. An inadequate contract set-up, due to inexperience

and mistakes in the contract design, or because of a poor regulatory framework, may lead to

necessary contract renegotiations as well. Further, weaknesses in risk simulations used during

investment appraisal may lead to risk underestimation and consequently the private party to

seek renegotiations aiming at more support from the government.