Risk Management in Transport PPP Projects
In the Islamic Countries
86
Brownfield
Greenfield project
Management and lease contract
Divestiture
Total
Sierra Leone
1
0
0
0
1
Uganda
1
0
0
0
1
Total
56
12
9
0
77
Grand Total
127
99
28
5
259
Source: Authors’ elaboration on data from the World Bank’s database on Private Participation in Infrastructure
(http://ppi.worldbank.org/)
In addition to the three criteria presented above, further relevant elements are represented by
the type and sub-type of PPI initiatives (see Tables overleaf restricted to the countries for which
at least 1 project is encoded in the PPI database). The type of project, e.g. the fact that an
infrastructure and/or service is already in operation (brownfield) or is new (greenfield),
adds/emphasizes risks in the set up and management of PPP solutions. Similarly, the type of
contract used for the PPI initiative, i.e. whether it involves one or more implementation steps of
the project (e.g. construction, financing, operation and maintenance of the
infrastructure/service), makes the governance and administration of PPP solutions more
articulated and complex.
Table 25: World Bank PPI Data for OIC Member Countries with at least one project encoded:
Sub-type of PPI
Build,
rehabilitate,
operate,
and transfer
Rehabilitate,
operate, and
transfer
Build,
operate,
and transfer
Management
contract
Rehabilitate,
lease or rent,
and transfer
Other
Total
Arab Group
Egypt, Arab
Rep.
2
0
10
2
0
0
14
Algeria
2
1
0
2
0
0
5
Jordan
4
0
0
1
0
0
5
Djibouti
1
0
2
1
0
0
4
Lebanon
0
0
1
1
0
0
2
Syrian Arab
Republic
0
1
0
0
0
1
2
Yemen, Rep.
1
0
1
0
0
0
2
Comoros
0
1
0
0
0
0
1
Iraq
1
0
0
0
0
0
1
Somalia
0
0
0
1
0
0
1
Sudan
1
0
0
0
0
0
1
Tunisia
1
0
0
0
0
0
1
Total
13
3
14
8
0
1
39
Asian Group
Malaysia
7
8
28
1
0
2
46
Turkey
9
6
17
0
1
8
41
Indonesia
7
6
12
0
0
0
25
Pakistan
3
2
7
0
0
2
14
Bangladesh
0
0
1
5
0
0
6
Kazakhstan
1
0
2
1
0
1
5
Albania
1
2
0
0
0
0
3