Previous Page  89 / 298 Next Page
Information
Show Menu
Previous Page 89 / 298 Next Page
Page Background

Risk Management in Transport PPP Projects

In the Islamic Countries

70

Phase 2: Pre-tender decision process

Risk identification and assessment in the pre-tender decision-making should logically follow

and build on the strengths and priorities identified through the strategic framework phase.

However, the focus in this phase is on specific projects or project types potentially suitable for

PPP funding. Independent of the procurement route selected, sound

technical-economic

studies

in this phase are essential to identify and evaluate key project risks ex-ante. However,

under a PPP procurement route the assessment of certain risks may become more critical and

the emphasis of the studies may reflect this, given the need to share risks with private parties

under a contract structure which may cover implementation from design to operation and asset

return. For example, where user charges are expected to support the remuneration of the

private party, traffic studies and travel behavior modelling should pay particular attention to

the willingness to pay of final users.

An important step is the

identification of the “PPP project” boundaries

. This relates to the

fact that the components of a project suitable for a PPP procurement route are not necessarily

identical to those of a similar project implemented through conventional procurement. To think

about the definition of the “PPP project” is thus part of good practice and a way to achieve a

viable alignment of incentives for the various parties. For instance, a project structured as PPP

may involve the inclusion of an existing asset as part of the concession agreement or other value

capture mechanisms, such as the ability to share land value uplifts generated by the project.

Box 6 Defining the “PPP project” – the Vasco da Gama bridge case

26

In the early 90’s the existing 25

th

April bridge connecting the Northern and Southern banks of the

Tagus river in the Lisbon metropolitan area in Portugal was operating beyond design capacity. The

bridge had been built in 1965 and the need for additional river crossing capacity had been

considered a national priority for quite a few years. In the early 90’s the Portuguese authorities

were aware of recent trends in the private financing of road infrastructure on estuarial crossings

such as the Dartford crossing and the Second Severn bridge. In addition, they viewed the new

crossing as technically challenging and private sector involvement, attracting international

expertise, as desirable. Thus, the Ministry of Public Works established GATTEL (Gabinete da

Travessia do Tejo em Lisboa) as a special-purpose agency charged with coordinating activities

related to the design and implementation of a new fixed crossing. It was then decided that the

project for a new crossing should be launched as a PPP based on a DBOT concession model.

One of

the key concepts of the concession

– also inspired by the experience in the United Kingdom –

was that the concessionaire would be given the operation of the existing bridge

.

This had the

function of giving the concessionaire an additional source of revenue, avoiding at the same

time competition from the existing infrastructure

. Thus, given the PPP delivery concept

adopted by the authorities,

the PPP project boundaries did not simply include the new asset

,

as it would have been the case under a conventional procurement model,

but also the existing

bridge

. The preliminary performance calculations, as often happens in the case of PPPs, were made

for multiple stakeholders.

26

This Box draws on Carbonaro et Al (2017).