Previous Page  217 / 298 Next Page
Information
Show Menu
Previous Page 217 / 298 Next Page
Page Background

Risk Management in Transport PPP Projects

In the Islamic Countries

198

contract; estimated capital cost; capital expenditure; stakeholders; tendering committee;

monitoring reports; KPIs; risk allocation. The updating of this database, however, has

unfortunately been discontinued, in view of likely new developments as regards the structure

of the unit and the overall government strategy towards investment projects. The government

is in fact expected to push for having a unified database for all infrastructure projects (not only

PPPs). Nevertheless, the database set up by the PPP unit does not include PPP projects managed

by ADC. The latter has not a formal system to keep track of the main features of its PPPs.

However, ADC always look back at existing PPP contracts when it has to develop a new PPP

project.

No evidence of sufficient risk-specific training activities has been found (neither at the central

level, nor in ADC), nor an effort to identify which are the most pressing knowledge gaps to be

filled in this field on the side of public administration. A learning by doing approach has been

mentioned by ADC.

In light of the fact that no transport PPP has yet reached its final stage in Jordan, it is instead too

premature to discuss ex-post evaluation.

5.5.8.

Conclusions and recommendations

Conclusions

In general terms, PPP transport projects in Jordan are characterized by a

well-developed

regulatory framework

, complemented by detailed (but not sector-specific) PPP guidelines.

Nevertheless, the implementation of such framework is still limited. Indeed, the two main PPP

project were implemented before the adoption of the current PPP law and the establishment of

the PPP unit. Also, at the moment the PPP framework does not apply to PPP projects promoted

by ADC in the Aqaba Special Economic Zone. These limits affect the risk management practices

as well. Despite having set out clear procedures for dealing with risks in PPPs, their

implementation in the transport projects is still at an infancy stage. So far, the low number of

transport PPP projects hampers the possibility for Jordanian authorities to gain significative

experience on transport-related risk management. Against this background, the following

conclusions can be put forward.

The national government is supportive of PPPs and has proved to be a reliable partner for

private operators. Thanks to political and monetary stability, as well as the established

cooperation with international organizations and IFIs,

PPPs in Jordan represent an

attractive investment opportunity

for foreign investors;

While on paper the legal framework and the PPP guidelines are appropriate,

nomeasures

appear to be taken to ensure an appropriate level of administrative capacity in risk

management practices

. As such, PPP guidelines run the risk of being overlooked;

While the establishment of the PPP unit proved to be useful to catalyze effort around PPPs

and to develop and promote the PPP guidelines,

the actual involvement of the PPP unit

in the whole cycle of the PPPs is questionable

. So far, they acted as a filter between

contracting authorities and the PPP Council rather than a coaching and mentoring body;