Previous Page  131 / 298 Next Page
Information
Show Menu
Previous Page 131 / 298 Next Page
Page Background

Risk Management in Transport PPP Projects

In the Islamic Countries

112

infrastructure to the China Harbor Engineering Company (CHEC),

the time plan was extended

to 2021

, with the completion of all infrastructure works by the Port Authority planned for 2020,

leaving one year for the works for the superstructure by the contractor.

In the construction phase,

no major issues

have been reported. The works for the widening and

deepening of the channel were completed in early 2019, in line with the revised time plan;

currently the civil works for the preparation of the terminal are ongoing, while the works for the

equipment of the terminal (assigned to the private party) have not yet started. On the side of the

state, the Port of Abidjan is in charge of the monitoring and supervision of the construction works,

and has in place a number of

measures for a proper management of the construction risks

,

such as:

Audit

are performed periodically, with minimum annual frequency, or more frequently

if needed; audits are performed directly by the Port Authority, that has the technical and

managerial skills required for controlling works in the domain of port infrastructure;

A

risk matrix

was developed to allow the identification of possible sources of risks, and

this is still in use to manage risks in the construction phase;

Annual reports

concerning the progress of works are delivered to the Ministry of

Transport, and ministry of budget is also involved to control expenditures.

Finally, although not required by the Ivorian Regulation, both the port and the terminal operator

are certified for quality and environment (ISO 9001 and ISO 14000).

Overall,

the PPP for the second terminal container in the Port of Abidjan is so far considered

successful

, as the overall project allowed to mobilize more than 1.4 billion euros in order to

increase container handling capacity at the Port and to remove the bottleneck due to the

insufficient depth and width of the Vridi channel. Also, once started, works have been so far

implemented according to the agreed time plan and the first phase of the project has been

successfully completed.

On the other side, some

weaknesses

can also be identified in this initiative. First of all, the overall

project will be completed only in 2021, that is 9 years after the launch of the tender in 2012. This

means that overall there is

a delay of at least 3 years compared to the original time schedule

(opening was foreseen in 2018). The main reasons of this delay were the difficulties in the

financial arrangements for the infrastructure works under the responsibility of the Port

Authority, which were finalized in 2015. Transferring this risk to the private party might have

resulted in earlier completion of the project; however, the huge total investment was presumably

too large for the private market, hence the adopted solution had the merit to improve the viability

of the initiative.

At another level, a concern of this operation is that reinforced the

almost total monopoly

position

of Bolloré Transports & Logistics (BTL) in logistics in the port of Abidjan as well as in

its hinterland connections. In fact, BTL enjoys a dominant position not only at the port (BTL is in

charge of both concessions for the two container terminals in the Port of Abidjan) but also in

railway (Sitarail) and trucking or logistics service provider industry (World Bank, 2014).

Sources: Author’s interviews, Port Autonome d’Abidjan (2018), World Bank (2014).