Previous Page  267 / 298 Next Page
Information
Show Menu
Previous Page 267 / 298 Next Page
Page Background

Risk Management in Transport PPP Projects

In the Islamic Countries

248

Specifically, about contract renegotiation, the Turkish Authorities consulted as part of the study

report that in order to mitigate the risk of contract renegotiation, which may require lengthy

and complicated negotiations, provisions are included in the contracts that relate to possible

adjustments of the contractual terms, without affecting the validity of the contract itself. In the

event a contract should be renegotiated to maintain its validity, this would anyway require

undergoing the same authorization steps for its approval at the stage of its original signature.

5.7.7.

End of contract

Contract return

Compared to the total PPPs in the transport sector the number of completed projects is very

limited and mainly related to the airport sector. No cases of

early termination

due to the

underperformance of the contractor at the construction and or operation stages appear to have

occurred, whereas one case of early contract termination has been identified based on existing

literature, which relates to the Sabuncubeli Tunnel PPP initiative, due to bankruptcy of the

contractor.

Early termination of PPP contracts is possible as per Turkish legislation in the event of severe

circumstances, such as grave underperformance or misconduct or negligence of the contractor

resulting in the violation of the PPP contractual provisions, bankruptcy, insolvency of the PPP

company and debt composition. Early termination may also be associated with

force majeure

events

. According to Turkish legislation and practice, these are also to be specified in the PPP

contract.

In case of early termination because of default of the contractor, the debt-based compensation

mechanisms has been recently adopted in some Turkish PPP transport projects, which as

described in previous sections above represents an incentive measure to attract foreign

investors and ensure bankability of PPP projects (European PPP Expertise Centre, 2013). If early

termination is determined by default of the public party resulting for instance in the lack of

payment of subsidies and or availability payments by the procuring authority, the latter retains

liabilities for the payment of financial compensations (European PPP Expertise Centre, 2013).

Box 48 Early termination: the case of Sabuncubeli Tunnel

Sabuncubeli Tunnel is a 4 km long tunnel acting as by-pass for the existing Izmir – Ankara

motorway in the mountainous region of Sabuncubeli, where the gradient of the motorway

increases, the speed decreases and road closures are possible in winter. The tunnel aimed to solve

these problems, increase road safety and reduce travel time by 30 minutes.

The contract was signed in 2011 with Kocoglu Construction, within the scope of a BOT contract,

with a total investment of 56.9 million USD in 2015 value. The total contract period was almost 13

years and the remuneration scheme of the project guaranteed also a minimum revenue for the

contractor (Özcan, 2018); tunnel opening was expected to be in 2015.

Nevertheless, in 2014 the private partner went into bankruptcy. KGM was forced to end the BOT

contract and retendered the project through traditional public procurement procedures (Özcan,

2018). Sabuncubeli Tunnel was finally opened to traffic in June 2018, 3 years later than expected.