Risk Management in Transport PPP Projects
In the Islamic Countries
225
The economic growth of the country has also been coupled with an increase in the use of PPP
projects. Over 240 PPP projects have been implemented in the country for a total budget volume
of nearly USD 140 billion (PSB 2018).
The following Table provides detailed information on the PPP projects implemented in Turkey
in the transport sector, according to interviews with the Turkish authorities performed as part
of this study.
Table 39: PPPs in the transport sector in Turkey
N
/
O
Project Name
Transport
mode
Type of PPP
Asset
already in
operation
Concession
Period
Procuring
Authority
1
Gebze – Orhangazi –
Izmir (incl. Izmit bay
pass and access
roads) motorway
Road
Build, operate,
and transfer
In
operation
23 years 11
months 14
days
KGM
2
Northern Marmara
motorway (incl. 3rd
Bosphorus section)
Odayeri-Paşaköy
(incl. access roads)
section
Road
Build, operate,
and transfer
In
operation
12 years 11
months 26
days
KGM
3
Northern Marmara
motorway (incl. 3rd
Bosphorus bridge)
Kurtköy-Akyazi (incl.
access roads) section
Road
Build, operate,
and transfer
Partially
8 years 9
months 8 days
KGM
4
Northern Marmara
motorway (incl. 3rd
Bosphorus bridge)
Kinali-Odayeri (incl.
access roads) section
Road
Build, operate,
and transfer
Partially
9 years 1
month 10 days
KGM
5
Menemen-Aliaga-
Candarli motorway
Road
Build, operate,
and transfer
No
13 years 1
month 5 days
KGM
6
Ankara – Nidge
motorway
Road
Build, operate,
and transfer
No
15 years 8
months 19
days
KGM
7
Kinali-Tekirdağ-
Canakkale-Savaştepe
motorway Malkara-
Canakkale section
(incl. 1915
Canakkale bridge)
Road
Build, operate,
and transfer
No
16 years 2
months 12
days
KGM