Previous Page  241 / 298 Next Page
Information
Show Menu
Previous Page 241 / 298 Next Page
Page Background

Risk Management in Transport PPP Projects

In the Islamic Countries

222

Box 43 Examples of extensions of the concession period

The original agreement for PLUS highway project singed in 1988 covered a 30-year period.

In 1999, in the context of the toll rate and indebtedness restructuring processes, the

government agreed to extend the concession period by twelve years to 2030. It was later

extended to 2038;

A 25-year concession contract was originally agreed on in 1993 for the Penang Bridge.

However, in 2009 to accommodate traffic volume an extra lane was built at the concession’s

expense. As a result, the concession period was extended for 3 years and 7 months up to

December 2021.

Follow up

UKAS maintains a database in which it tracks records of all PPPs projects in all sectors

,

including transport (e.g. costs, contract duration, etc.). This database is used as a reference tool,

e.g. in the risk identification exercise.

Despite this internal database, the process of learning from experience mainly consists in

informal information sharing between senior officers within UKAS regarding past projects and

there is no evidence of a systematic approach towards ex-post evaluation.

To enhance internal capacity-building, UKAS organizes also some

special training sessions

for

its staff, involving also experts such as from theWorld Bank and Asia Development Bank in order

to spread knowledge about PPP models and best practices, as well as how to implement PPPs

efficiently.

5.6.8.

Conclusions and recommendations

Conclusions

What emerged from the evidence collected in the Malaysian case study is a

decennial

experience

in the design and implementation of transport PPPs and the management of the

involved risks. This has been developed also thanks to a strong political and strategic support

over the years from the governments.

The existence of UKAS is key asset.

The unit, thanks to the internally developed knowledge

and technical skills, is able to provide effective support to the ministry of transport in the form

of consultancy services and technical assistance for the project selection and implementation.

In particular,

the role of UKAS in the phases of contract negotiation

(including risk

identification and assessment)

emerges as pivotal.

From the analysis of the institutional arrangements in place, it is clear how the core

competencies regarding PPPs are within UKAS. At the same time, this highlights the disparities

in the level of competences between UKAS and the experts within the ministry of transport. This

situation could entail some risks, due to the fact that the transport ministry has a key role in the

monitoring of complex risks potentially arising during the operation phase of the PPP project.