Improving Transport Project Appraisals

In the Islamic Countries

70

Figure 3.3: Responsible parties for preparing transport project appraisals

Source: survey

Quality review is another important aspect of project appraisals. The majority of the

respondents indicated that an internal department of the Ministry is responsible for the quality

review. In 25% of the cases, the quality review is also done by an external

institution/organisation, as illustrated i

n Figure 3.4.

Figure 3.4: Responsible party of quality review of project appraisals

Source: survey

Thirty-eight percent of the respondents indicated that project appraisal reports are made

publically available. It was also found that it is more common to conduct an informal stakeholder

consultation outside the parliamentary process, rather than a formal stakeholder consultation

through parliamentary processes. Moreover, local governments and sector organisations are

involved in the stakeholder consultation, while households are not.

27%

9%

64%

Public agencies

Private consultants and universities

Both

75%

25%

Internal department of Ministry External institution/organisation