Previous Page  15 / 49 Next Page
Information
Show Menu
Previous Page 15 / 49 Next Page
Page Background

Proceedings of the 14

th

Meeting of the

Transport and Communications Working Group

11

in less developed countries, as the assessment needs to be carried out on a case-by-case basis,

taking into account context- and project-specific considerations.

Question:

How should the optimum risk-sharing be achieved?

Answer:

For the achievement of an optimum risk-sharing among the public and private parties,

specific economic assessments at the project level can be particularly useful, on which wide

literature already exists. As an example, VfM assessments based on well-identified risk

allocations can provide indications on the way to achieve the highest VfM by appropriately

allocating risks. In addition, to achieve an optimum risk sharing, it may be important to take into

consideration the need for a balance between benefits for society and the return for the private

investor.

In conclusion, Ms. PANCOTTI expressed agreement with an observation put forward by a

representative of the OIC Member Countries, who stated that for certain transport PPP projects

it could be appropriate to grant some degree of freedom of intervention to the private operators

(particularly in relation to unsolicited proposals), as long as there is an adequate regulatory and

legislative framework in place. As a final remark, the consultant noted that globally a decreasing

trend for unsolicited proposals in PPPs has been observed, but that at the same time there is an

increasing awareness in public authorities of the need to regulate such proposals. Current

Situation of the OIC Member Countries in terms of Risk Management in Transport PPP Projects

and the Lessons Learnt from the Selected Case Studies.

4.

Current Situation of the OIC Member Countries in terms of Risk Management in

Transport PPP Projects and the Lessons Learnt from the Selected Case Studies

Mr. Roberto ZANI, director at Tplan and co-author of the research report delivered his

presentation with a focus on the status of risk management practices of transport PPP projects

in OIC Member Countries and lessons learned from six case studies. At the outset, he presented

the results of the desk research and country visits conducted as part of the research.

Selection of the case studies and methodological background

Mr. ZANI started his presentation providing an overview of the approach adopted for the

identification and selection of the six OIC Member Countries subject of case study analysis and

the methodology used to perform the research.

The identification and selection of the countries for

case study

analysis were based on the

information encoded in theWorld Bank’s database on Private Participation in Infrastructure.

According to the total number of projects included in the database, out of the 57 OIC Member

Countries, only 14 registers a number fo PPPs in the transport sector equal or higher to 5. 21