Previous Page  11 / 49 Next Page
Information
Show Menu
Previous Page 11 / 49 Next Page
Page Background

Proceedings of the 14

th

Meeting of the

Transport and Communications Working Group

7

3.

Procurement and contracting:

The third phase of the conceptual framework covers the following aspects: procurement

strategies; PPP contractual arrangements; performance metrics; remuneration.

Analytical points:

High quality of tender documentation reduces the overall risk vulnerability for the public sector.

Preparing PPP contracts revolves mainly around risk allocation, i.e. defining which party is

expected to assume each risk. In this regard, a useful tool is represented by the risk matrix, i.e. a

tool detailing, for each risk, whether it is borne by the public sector, by the private sector or

whether it is shared. The general risk matrix developed as part of the conceptual framework

indicates that political and legal risks are generally borne by the public sector; macroeconomic

risks are generally shared; risks related to financial credit, design, construction, operation, and

financial sustainability are generally allocated to the private sector; finally, force majeure and

early termination risks are usually shared and need to be assessed on a case-by-case basis.

PPPs are defined by the fact that remuneration to the private sector is commensurate to the

service delivered. In this regard, performance metrics are directly linked to the ongoing activity

of risk monitoring during construction and operation.

Key messages from the literature review and good practices:

In the procurement phase, there is a need to build on VfM considerations. This has a

twofold meaning: first, during the tender and then in the contracting phase, there must

be consistency with the risk allocation identified in the VfM assessment; second, if

negotiations take place and the allocation of risks is modified, a VfM assessment should

be carried out anew;

With regard to negotiations, there is a need to raise awareness of likely legal and

technical asymmetries in negotiation skills between the public and the private sector;

It is essential to establish at project level a skilled tender management team to direct

tender preparation, publishing, and award.

4.

Construction and asset delivery:

The fourth phase of the conceptual framework covers the following aspects: management of

risks during design; management of risks during construction.

Analytical points:

Design risk consists of defects in design resulting in the requested service standards not being

met, or in an increase in operating costs. As regards construction risks, these can be caused by

either internal factors (defects in methods used, negligence by a private party, inadequate cost