Previous Page  265 / 298 Next Page
Information
Show Menu
Previous Page 265 / 298 Next Page
Page Background

Risk Management in Transport PPP Projects

In the Islamic Countries

246

Remuneration

BOT PPPs implemented under responsibility of KGM, DHMI and AYGM, with the exclusion of

port and touristic marinas, are remunerated based on fixed demand guarantees, i.e. the

contractors receive a subsidy from the procuring authority as long as the demand does not reach

the threshold set by the procuring authority in the tender specifications. When the traffic

exceeds the demand guarantee threshold, no subsidy is paid to the contractor. Revenue sharing

mechanisms are also foreseen for some highway projects, including the Eurasia tunnel, and for

airport PPPs (see also Section 5.7.6 below).

For

BOT commercial ports and touristic marinas

under the responsibility of AYGM, as well

as for

TOR projects

in the airport sector under the responsibility of DHMI, there is no

remuneration to contractors. Instead, the procuring authority is receiving a concession fee

offered by the contractor at the tendering stage.

5.7.5.

Construction and asset delivery

Management of risks during design and construction phases

Preliminary project design documentation, including detailed technical specifications, are

elaborated by the procuring authorities for BOT schemes. Environmental Impact Assessment

studies are also elaborated at the pre-tendering stage. Notwithstanding the fact that changes

and adaptations are possible at the construction design stage under the responsibility of the

contractor,

technical design risks

are retained by the procuring authorities. However, this does

not apply to disruptive technology-related risks. As mentioned in previous sections above the

fact that the General Directorate of Highways (KGM) and General Directorate of State Airports

(DHMI) are following the projects in the respective technical field of planning and operation is

a risk mitigation factor in this respect.

The contractor is responsible for the

timely construction of the project

and the risks

associated with its implementation according to the foreseen schedule. In case of

underperformance, according to the Turkish law, the procuring authority may apply penalties

or terminate the contract if the delays are attributable to the contractor (Özeke, 2019). For

instance, provided that the contractor is responsible to submit the applications and accomplish

the administrative procedures to develop and implement the project in a timely and professional

manner, the case of delays due to issues in the land acquisition processes or additional permits

and licenses attributable to delays under the responsibility of the public sector do not imply the

application of penalties and are likely to result in an extension of the PPP contract. As

commented above, a systemic monitoring process is however also foreseen by law, which

represents a key mitigation factor towards the timely implementation of the project.

The monitoring system also relates to the early identification of

defects

. Defects and defects

liability periods are usually specified in the PPP contracts which could be allocated to the

procuring authority (or designer company if different) and the contractor. In the event of

identification of defects under the responsibility of the contractor, the procuring authority may

request the repair of the defect, apply a penalty or terminate the contract (Özeke, 2019).