Previous Page  192 / 298 Next Page
Information
Show Menu
Previous Page 192 / 298 Next Page
Page Background

Risk Management in Transport PPP Projects

In the Islamic Countries

173

Contract renegotiation

Amendments or changes to the contract terms are allowed by legislation

that need to take

the form of contractual amendments. Changes in the ownership/contract assignment are also

possible specified that the replacing entity has also to explicitly assume contractual obligations

in front of the procuring authority. The state may also exercise its pre-emptive right on the

transfer of equity shares. Amendments may be done by the line Ministry without an external

control of the National Regulatory Authority for Public Procurement if changes do not affect the

denomination of the contracting parties, the technical and financial guarantees and the

contractual period, and when its amount or cumulated amounts of the different amendments is

below 10% of the initial amount of the contract. Under different circumstances external control

from the authority is required. The National Regulatory Authority for Public Procurement also

exercises control on the amendments foreseeing an increase higher than 15% of the original

contract value for services and studies and 20% for the procurement of public works.

Amendments to the economic terms of the contract are indeed possible as long as they are not

related to causes attributable to any of the involved parties. Similarly modifications to the

original contract are also possible to restore the financial sustainability of contracts if the causes

of the imbalances are not attributable to the SPV.

Risk allocation cannot be modified as part

of contractual amendments procedures

(WB, 2018).

Dispute resolution mechanisms are also foreseen by public procurement law

which

includes amicable resolution in first instance. Mediation and arbitration measures include

international arbitration as well as investor-state arbitration as Algeria adopted the 1958 New

York Convention on the Recognition and Enforcement of Foreign Arbitral Awards, which

entered into force in the country on 9 September 1998. Algeria is also member of the

International Centre for Settlement of Investment Disputes (ICSID Convention). The National

Regulatory Authority for Public Procurement is also endowed with a national mechanism of

conflict resolution for the solution of disputes between the parties involved in public

procurement processes (WB, 2018).

Concerning

force majeure

, public contracts shall specify all the cases of force majeure. Force

majeure events determine the suspension of the project implementation time-schedule.

Accordingly delays attributable to force majeure events will not result in the application of

penalties (WB, 2018).

5.4.7.

End of contract

Contract return

According to the public procurement code

at the stage of contract resolution the

infrastructure shall be returned by the parties in optimal conditions

. If this may not be

possible, compensation measures may be adopted (WB, 2018). In absence of a dedicated PPP

regulatory framework, the public procurement law is not specific in terms of duration of the PPP

contracts. The three PPP contracts relating to the development and management of port